$7M, 7-bridge construction project

$7M, 7-bridge construction project on I-70 starts April 17, 2017

Milestone Contractors plans to set construction signs along I-70 on April 17, 2017 for a $7.2 million project to replace or maintain and preserve seven bridges in Hancock and Henry counties.

Overnight lane closures on I-70 can be expected in the following three construction zones starting on or after April 17 between 9 p.m. and 6 a.m. as crews set temporary concrete barriers and pave shoulders in preparation for future traffic shifts.

All work on the contract is expected to be complete by December. Specific dates and traffic restrictions at each bridge location will be announced in advance of each phase of construction.

Rebuilding two bridges over Six Mile Creek

Milestone will rebuild twin I-70 bridges over Six Mile Creek, which is located near mile 112 west of the Hancock-Henry county line and State Road 109 (Exit 115).

Work is scheduled to begin on or after April 19. Two lanes in each direction will be shifted to the right for approximately one month while temporary pavement is constructed in the median that will be used for crossing one lane of traffic across the median during subsequent phases of construction.

During construction of each (eastbound and westbound) bridge, one lane of that direction of traffic will be temporarily shifted across the median to share the other side of the interstate with the opposing direction of traffic separated by concrete barriers. The other lane will remain on the side of the interstate under construction and shifted to one half of the bridge as each structure is rebuilt one half at a time.

Two lanes will be maintained in both directions except for overnight lane closures between 9 p.m. and 6 a.m.

Rehabilitating two bridges over Brandywine Creek

Milestone will repair and preserve twin I-70 bridges over Brandywine Creek, which is located just east of State Road 9 (Exit 104) in Hancock County.

Starting in late May, two lanes of traffic in each direction will be temporarily shifted to the left, toward the median, until later this summer while construction takes place on the right half of the bridges. The second phase, which is scheduled to begin in August, will shift both lanes toward the right shoulders as work is completed on the median side of the bridges.

Two lanes will be maintained in both directions of I-70 except for overnight lane closures between 9 p.m. and 6 a.m. Interchange ramps at State Road 9 are expected to remain open with the exception of some weekend closures starting at 9 p.m. on Friday until 6 a.m. on Monday.

Overlaying two bridges over Montgomery Creek

Milestone will repair and preserve twin I-70 bridges over Montgomery Creek, which is located just east of State Road 109 (Exit 115) in Henry County.

Work is scheduled to begin in June. Two lanes will be maintained in both directions except for overnight lane closures between 9 p.m. and 6 a.m. and during some weekends, when one lane may be closed for concrete work starting at 9 p.m. on Friday until 6 a.m. on Monday.

Interchange ramps are expected to remain open with the exception of the State Road 109 entrance ramp to eastbound I-70, which may be closed starting at 9 p.m. on Friday until 6 a.m. on Monday for concrete work in the eastbound right lane.

Bridge deck overlay on Hancock County Road 850 East

Milestone will close the Hancock County Road 850 East bridge over I-70 starting on or after May 15 for about two months to apply a modified concrete overlay to the bridge deck. During the closure, county road traffic will be detoured to cross the interstate using County Road 600 East via County Roads 250 and 300 North.

Stay informed

Follow @INDOTEast on Twitter and INDOT East Central on Facebook. Find links to all INDOT social media pages at http://bit.ly/INDOTsocial.

SOURCE: News release from Indiana Department of Transportation